A major challenge faced in the course of this project was building a completely new plateau covering the area of several thousand square meters for the future transformer substation and the connection switchgear facility, while preserving the natural environment at the same time.
In addition to the execution of foundations, a lot of effort was invested in the installation of a 17 km long 110kV transmission line through highly inaccessible terrain, between valleys and steep slopes where classic methods of transportation and installation of steel pole structures were not sufficient.