In order to increase the capacity and reliability in the supply of electricity to the consumption area of ​​the center of Belgrade, Kodar has begun work on replacing the existing 110kV oil cable with a new dry 110kV cable. In order to overcome the complexity of performing works along the busiest roads in Belgrade in the length of 4.5 kilometers, for the first time in the eastern part of Europe, 110kV cables will be installed with a cable entanglement system.

Through training and coaching, we have mastered the use of this technology and thus enabled the application of working methods that avoid open trenches and which allow easy replacement of future cables. We organized the project in such a way as to optimize the work of our teams and at the same time enable the citizens of Belgrade to function normally.