The installation of the anemometer column with a height of 110.60m has been completed
Kodar | November 30, 2022
The installation of the anemometer column with a height of 110.60m has been completed
In 45 days, we completed the assembly, including the construction of the foundation and the erection of the steel structure, of the anemometer three-band lattice steel column with a height of H=110.60m. The object is of a temporary nature and is being carried out in order to install equipment for measuring wind direction and speed, temperature and air density at...
The Langedijk – St Pancras project received the best rating
Kodar | November 30, 2022
The Langedijk – St Pancras project received the best rating
Our company received the best rating for the Langedijk – St Pancras project of all current FTTH development projects within the KPN network in the Netherlands. With an average rating of 9.38, we once again confirmed the quality of our services and the dedication of our teams. We are proud of this achievement and grateful to all our colleagues who...
The start of a new FTTH network development project for KPN B.V.
Kodar | November 30, 2022
The start of a new FTTH network development project for KPN B.V.
At the end of September, we started the implementation of a new FTTH network development project for the needs of KPN B.V. The Velsen-Noord project includes the construction of an optical network for 2,422 new users in the territory of the municipality of Velsen who will be able to access the optical Internet. This project is a continuation of the...
Construction of the FTTH network in the city of Hellevoetsluis
Kodar | November 30, 2022
Construction of the FTTH network in the city of Hellevoetsluis
For the needs of Open Dutch Fiber B.V., we will build a FTTH network for 17,900 users in the city of Hellevoetsluis and provide them with access to super-fast optical Internet. Our colleagues have successfully completed the delivery and installation of the second POP (point of presence) out of a total of four as provided for in the network plan....
Kodar Energomontaža in the second quarter of 2022
Kodar | October 17, 2022
Kodar Energomontaža in the second quarter of 2022

– By the end of August, we managed to realize over 70% of the contracting plan for 2022. Our colleagues from the sales sector realized the set goals with their efforts and contracted new projects that will contribute to the further development of our company. We are confident that we will implement the contracted projects on time and within the…

First Media facade in the Balkans
Kodar | February 28, 2022
First Media facade in the Balkans

As part of the project “Belgrade Waterfront”, on the tallest building in the Balkans (168m) – “Belgrade Tower”. Kodar through an EPC contract, conceived, designed, delivered equipment and performed works on the first job of this type in Serbia, the construction of a media facade. We have enabled all 9,317 individually controlled LED luminaires to serve as a dynamic backbone…

We successfully completed a two-year project in the Netherlands for KPN B.V.
Kodar | February 15, 2022
We successfully completed a two-year project in the Netherlands for KPN B.V.

By building an optical network, our company has built an information highway for 32,000 households in the Netherlands. After two years of work, our team of over 100 people has successfully overcome all the challenges of the new market and thus contributed to our company being at the very top in terms of service quality index and customer satisfaction. Citizens…

Start of 110kV underground cable replacement
Kodar | February 15, 2022
Start of 110kV underground cable replacement

In order to increase the capacity and reliability in the supply of electricity to the consumption area of ​​the center of Belgrade, Kodar has begun work on replacing the existing 110kV oil cable with a new dry 110kV cable. In order to overcome the complexity of performing works along the busiest roads in Belgrade in the length of 4.5 kilometers,…

60km of new transmission line
Kodar | February 15, 2022
60km of new transmission line

Kodar has completed work on a very important project. Construction of 400 kV transmission line, TS Kragujevac 2 – TS Kraljevo 3. The construction of 400 kV transmission line from substation TS Kragujevac 2 to substation TS Kraljevo 3, total length of 60 kilometers, as well as reconstruction of substation TS Kraljevo 3 and raising from 220 kV to 400…

Completed works on the construction of the substation Belgrade 45 - Sava Amphitheater
Kodar | April 12, 2020
Completed works on the construction of the substation Belgrade 45 – Sava Amphitheater

Within the shopping center “Gallery”, and for the needs of powering part of the promising consumption of Belgrade on water, through the EPC contract, we built a modern transformer station that will enable the development of this part of the city of Belgrade. This project is specific because we have designed and built the first urban 110 / 10kV substation,…